402 W. Broad St.
Freeport, TX
May 8, 2008
To all HFH volunteers,
Habitat is nearly ready to start its third house build of 2008 (House #65). It is at 402 W. Broad St. in Freeport (on the corner next to the last house we built in Freeport). The following is a map to the build site, or click on the following link to display the map as you choose.
http://www.mapquest.com/maps/402+W.+Broad+St.+Freeport+TX/

A tentative schedule of the work planned for each day is at the end of this e-mail. Note, there are three days at the end of the build in which specialized work will be done, and volunteers will not be needed. Of course, this schedule may change a little as the work proceeds and the personnel and weather can better be assessed.
Build Information:
Sign-in and breakfast are from 7:15-7:45 a.m. each day at the hospitality tent at the site. Status reports and devotional are from 7:45-8:00 a.m. Work starts about 8:00 a.m. and runs until about 5:00 p.m. However, you can come and go at any time. Breakfast, lunch, water, lemonade and snacks will be provided during the regular work days except as noted in the build schedule.
Any and all volunteers are welcome to participate on any of the work days. There will be crew leaders present to direct the work and to show anyone how to do an unfamiliar job. Most tools will be provided, however, you might want to bring your own hammer, tape and/or tool belt if you have them. So, find a job you want to do, or take advantage of on-the-job training, and come help. Please note that there are age restrictions for safety reasons.
Remember, much of the build information, pictures from past builds and other information is available at Habitat’s web site. You can access it through the following link: http://www.habitatsbc.org/ . Please note that you can submit a Volunteer Information Form from the web site if you want to be notified of future build information.
Hope to see you at the build.
Jim Erskine
Habitat for Humanity Volunteer Coordinator
HOUSE NO. 65
BUILD SCHEDULE
M=meals provided.
nM=no meal
Th (May 8) M
Layout
Precuts - rafters, plates, beams, caps
Check windows, assemble doors
Mark plates
Fri (May 9) M Build walls stand, square.
Get tub
Sat (May 10) M Delivery of windows and ext. doors, etc.
Set gables, set trusses, porch posts
Sheath walls, windows
Rough plumbing, electrical
Mon (May 12) M Finish porch roof framing
Deck roof and dry in
Rough AC
Stairwell, Ext. doors,
Install dead wood
Blue board ext.
Schedule inspection
Tue (May 13) M Delivery of insulation, sheetrock
Inspect
Insulate interior
Start vinyl
Wed (May 14) M Sheet rock
Mud
Vinyl
Thu (May 15) M Deliver int. doors, assemble
Sheet rock
Cont. mudding,
Vinyl
Fri (May 16) M Cover windows
Texture
Trim
Rough grade outside
Sat (May 17) M Trim, caulk
Prepare for paint
Mon (May 19) nM Paint (no volunteers needed)
Tue (May 20) nM Floor covering (no volunteers needed)
Wed (May 21) M Electrical
Plumbing
Cabinets
Finish trim
Thu (May 23) nM Formica (no volunteers needed)
After side walk and drive is in, schedule final grading and landscaping.
Also, schedule electrical inspection and gas inspection